Howe Drive 2012
Third and Final Phase
Tuesday, July 31, 2012
today's crews
a day of drywalling
Monday, July 30, 2012
today's crew
spray insulation has started
drywalling in the other two units has started
painting of the baseboards has started
joists in the last unit
Thursday, July 26, 2012
drywall for the next two units
connecting the vents
a day of vapour barrier
Wednesday, July 25, 2012
drywalling has started
insulation being put in
safety barriers being put up
leveling out the gravel
our multi task window and siding crew
another birthday
closing in the end of the unit
Tuesday, July 24, 2012
today's crew
the siding crew
also the window crew
carrying in the insulation
nailing in the bracing
putting up the knee wall
Monday, July 23, 2012
flooring on second last unit
blue board and house wrap going on
closing in the dormers
closing in the pipes
concrete steps are in place
shingling is ongoing
at the end of the day
Friday, July 20, 2012
today's group from Gore mutual
putting up the blue board and weather shield
getting the windows ready
getting the window openings ready
putting in the bracing
screwing down the floor
at the end of the day